Aurora Colorado

  • Asked to shut down old manufacturing plant and relocate to new location in 30 days.
  • City processing time was minimum of 6 months.
  • Worked with the Mayor and City of Aurora to streamline their process, received a commendation from the Mayor and City manager.
  • Reduced the process time to 2 weeks, moved the plant and performed remodel of new plant within 30 days. Worked to re-write the City of Aurora Planning Dept. procedures.

 
Pensacola Florida

  • After Hurricane Katrina, the lumber yard and manufacturing facilities were red tagged by City.
  • Immediately worked with City officials, Fire Dept. and client to remove those red tags, rebuild damaged facilities and reopen locations.
  • Location opened far sooner than similarly damaged businesses.

 
Succasunna, New Jersey

  • After retail and manufacturing facility lost in a large fire we found new location secured it for clients use.
  • Re configured clients' process and retail layout for 30% greater efficiency and 25% increased sales in just 60 days.
  • Located 100 year old photograph showing additional access points to site.
  • Petitioned City and council and won the rights to reopen old access points providing improved delivery and traffic access to location.

 
100 Wickes Locations

  • Tasked with analysing each Wickes Lumber location, truss manufacturing plants and Cabinet manufacturing facilities.
  • Analyse to highest best use, closure, relocation, sub lease, sale etc.